OWNER PROJECT |
: |
PC North Madura II Ltd |
CONTRACTOR |
: |
Consortium PT Gunanusa Utama Fabricators and PT Hafar Daya Konstruksi
|
PROJECT |
: |
Provision of Engineering, Procurement, Construction, Installation and Commissioning (EPCIC) of Integrated Wellhead Central Processing Platform (WHCPP), Subsea Pipeline and Pipeline End Terminal (PLET) for Hidayah Field Phase 1 Development Project
|
LOCATION |
: |
North of Madura Island, East Java Sea |
AWARDED |
: |
9 November 2024 |
PO/ CONTRACT NO. |
: |
4850000716 |
DESCRIPTION |
: |
EPCIC of 1 (one) Integrated Wellhead Central Processing Platform (WH-CPP)
- Topside with weight 4,512 MT
- Substructure (6 legs Jacket) with weight 4,200 MT including pile, boat landing and mating cone
- Pipeline 16” x 1 KM (CS)
- PLET 1 ea
- Flexible riser 16”
- Supply of Remote Central Control Room (CCR) which installed at Hidayah FSO
|